All sub-structure works are now complete at our site in Unsworth and we are 70% complete with drainage. Screeding has commenced and scaffolding is progressing in preparation for the roof and brickwork to start. Timber frame is also due to commence over the next couple of weeks.

We have also had our first site visit from Considerate Constructors at the beginning of the month, receiving a positive report of “Very Good”. Our team are continuing to work with all suggestions given, to better our benchmark score within our next site visit.